(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
(7) Subsection 7 (3) and sections 134, 180, 224 to 230, 235 and 239 come into force on January 1, 2012.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(7)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 9.25.3.1.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
(7) Subsection 7 (3) and sections 134, 180, 224 to 230, 235 and 239 come into force on January 1, 2012.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(7)
Provenance
OBC 1997 · continues from 9.25.3.1. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 503/09, cl. 180 · ext v1 →
In force 2012-01-01
Next: O. Reg. 503/09, cl. 180 · ext (not in force until 2012-01-01) v1 →
OBC 2012 · continues as 9.25.3.1. — Pro
9.25.3.1. — Required Barrier to Air Leakage
Comparing versions
Changed text stands out · unchanged is dimmed
v0 base
Earlier · viewing · 2006-12-31(1) Thermally insulated wall, ceiling and floor assemblies shall be constructed so as to include an air barrier system that will provide a continuous barrier to air leakage,
(a) from the interior of the building into wall, floor, attic or roof spaces sufficient to prevent excessive moisture condensation in such spaces during the winter, and
(b) from the exterior inward sufficient to prevent moisture condensation on the room side during winter.
v1 O. Reg. 503/09
Later · 2012-01-01(1) Wall, ceiling and floor assemblies that separate conditioned spaces from unconditioned spaces shall be constructed so as to include an air barrier system that will provide a continuous barrier to air leakage,
(a) from the interior of the building into wall, floor, attic or roof spaces sufficient to prevent excessive moisture condensation in such spaces during the heating season, and
(b) from the exterior inward sufficient to prevent moisture condensation on the room side during the heating season.
(2) The continuity of the air barrier system shall extend throughout the basement.
Provenance
OBC 1997 · continues from 9.25.3.1. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 503/09, cl. 180 · ext v1 →
In force 2012-01-01 comparing ×
Next: O. Reg. 503/09, cl. 180 · ext (not in force until 2012-01-01) v1 →
OBC 2012 · continues as 9.25.3.1. — Pro