9.20.13.
Version 0 — in force 31 December 2006
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 9.20.13.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 9.20.13.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 9.20.13. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 9.20.13. — Pro
9.20.13. — Control of Rain Water Penetration
Content not available for this version.
9.20.13.1. — Materials for Flashing
(1) Material used for flashing shall conform to Table 9.20.13.1.
(2) Aluminum flashing in contact with masonry or concrete shall be effectively coated or separated from the masonry or concrete by an impervious membrane.
Text · e-Laws consolidated snapshot
Column 1 | Column 2 | Column 3 |
Material | Minimum Thickness, mm | |
Exposed Flashing | Concealed Flashing | |
Aluminum | 0.48 | — |
Copper | 0.46 | 0.46 |
Copper or aluminum laminated to felt or kraft paper | — | 0.05 |
Hot dipped or galvanized steel | 0. 33 | 0.33 |
Lead sheet | 1.73 | 1.73 |
Polyethylene | — | 0.50 |
Roll roofing, Type S | — | standard |
Zinc | 0.46 | 0.46 |
9.20.13.2. — Fastening of Flashing
(1) Fastening devices for flashing shall be corrosion-resistant and where metal flashing is used, shall be compatible with the flashing with respect to galvanic action.
Text · e-Laws consolidated snapshot
9.20.13.3. — Location of Flashing
(1) Flashing shall be installed in masonry and masonry veneer walls,
(a) beneath jointed masonry window sills,
(b) over the back and top of parapet walls,
(c) over the heads of glass block panels, beneath weep holes, and
(d) over the heads of window and door openings in exterior walls when the vertical distance between the top of a window or door frame and the bottom edge of the eave exceeds one-quarter of the horizontal eave overhang.
(2) Throughwall flashing shall be provided in a masonry veneer wall such that any moisture that accumulates in the air space will be directed to the exterior of the building.
Text · e-Laws consolidated snapshot
9.20.13.4. — Extension of Flashing
(1) A flashing may be deleted when the masonry at the sill of a wall opening or the top of a wall is protected by an impervious non-jointed masonry coping that conforms to Article 9.20.13.12.
(2) When installed beneath jointed masonry window sills and jointed masonry copings or over the heads of openings, flashing shall extend from the front edge of the masonry up behind the sill or lintel.
Text · e-Laws consolidated snapshot
9.20.13.5. — Flashing for Weep Holes in Masonry Veneer/Masonry Walls
(1) Flashing beneath weep holes in cavity walls and masonry veneer/masonry back-up walls shall,
(a) be bedded not less than 25 mm in the inside wythe,
(b) extend to not less than 5 mm beyond the outer face of the building element below the flashing, and
(c) be installed with a nominally horizontal slope toward the outside wythe.
Text · e-Laws consolidated snapshot
9.20.13.6. — Flashing for Weep Holes in Veneer
(1) Flashing beneath weep holes in masonry veneer over masonry back-up walls shall conform to the flashing requirements for cavity walls and masonry veneer/masonry back-up walls in Article 9.20.13.5.
(2) Flashing beneath weep holes in masonry veneer over wood-frame walls shall be installed so that it extends from a point not less than 5 mm beyond the outer face of the building element below the flashing to a point 150 mm up the wood frame wall.
(3) Where the frame wall is sheathed with a sheathing membrane, a non-wood-based rigid exterior insulating sheathing or a semi-rigid insulating sheathing with an integral sheathing membrane, the flashing shall be installed behind the sheathing membrane or insulating sheathing.
(4) Flashing described in Sentence (2) is permitted to conform to the requirements for concealed flashing in Table 9.20.13.1.
Text · e-Laws consolidated snapshot
9.20.13.7. — Flashing Joints
(1) Joints in flashing shall be made watertight.
Text · e-Laws consolidated snapshot
9.20.13.8. — Required Weep Holes
(1) Weep holes spaced not more than 800 mm apart shall be provided at the bottom of,
(a) cavities in cavity walls, and
(b) cavities or air spaces in masonry veneer walls.
(2) The cavities or air spaces described in Sentence (1) shall include those above lintels over window and door openings required to be flashed in conformance with Article 9.20.13.3.
(3) The weep holes required in Sentence (1) shall be in a location such that any water that collects in the cavity or space will be directed to the exterior of the building.
Text · e-Laws consolidated snapshot
9.20.13.9. — Protection of Interior Finish
(1) Except as provided in Sentence (3), where the interior finish of the exterior walls of a building is a type that may be damaged by moisture, exterior masonry walls, other than cavity walls or walls that are protected for their full height by a roof of a carport or porch, shall be,
(a) parged on the interior surface, and
(b) covered with No. 15 breather-type asphalt-saturated paper conforming to CAN/CGSB-51.32-M, “Sheathing, Membrane, Breather Type”, and shall be lapped not less than 100 mm at the joints.
(2) In situations described in Sentence (1), flashing shall be provided where water will accumulate, to lead it to the exterior.
(3) Where the insulation effectively limits the passage of water vapour and is applied by a waterproof adhesive or by mortar directly to the masonry, the requirements for sheathing paper do not apply.
Text · e-Laws consolidated snapshot
9.20.13.10. — Mortar Droppings
(1) Cavity walls shall be constructed so that mortar droppings are prevented from forming a bridge to allow the passage of rain water across the cavity.
Text · e-Laws consolidated snapshot
9.20.13.11. — Caulking at Door and Window Frames
(1) The junction of door and window frames with masonry shall be caulked in conformance with Subsection 9.27.4.
Text · e-Laws consolidated snapshot
9.20.13.12. — Drips Beneath Window Sills
(1) Except for wall openings located less than 150 mm above ground level, where a concealed flashing is not installed beneath window and door sills, such sills shall be provided with an outward slope and a drip located not less than 25 mm from the wall surface.
Text · e-Laws consolidated snapshot
Provenance
OBC 1997 · continues from 9.20.13. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 9.20.13. — Pro