OBC 2006 › Division B
4.1.8.10.
Version 0 — in force 31 December 2006
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 4.1.8.10.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 4.1.8.10.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · split from 4.1.9.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 4.1.8.10. — Pro
4.1.8.10. — Additional System Restrictions
(1) Except as required by Clause (2)(b), structures with a Type 6 irregularity, Discontinuity in Capacity – Weak Storey, as described in Table 4.1.8.6.v1, are not permitted unless IEFaSa(0.2) is less than 0.2 and the forces used for design of the SFRS are multiplied by RdRo.
(2) Post disaster buildings shall,
(a) not have any irregularities conforming to Types 1, 3, 4, 5 and 7 as described in Table 4.1.8.6.v1, in cases where IEFaSa(0.2) is equal to or greater than 0.35,
(b) not have a Type 6 irregularity as described in Table 4.1.8.6.v1, and
(c) have an SFRS with an Rd of 2.0 or greater.
(3) For buildings having fundamental lateral periods, Ta, of 1.0 s or greater, and where IEFvSa(1.0) is greater than 0.25, walls forming part of the SFRS shall be continuous from their top to the foundation and shall not have irregularities of Type 4 or 5 as described in Table 4.1.8.6.v1
Editor's note
In Sentence (2) of this article, the as-filed O. Reg. 350/06 writes the defined term as 'Post disaster buildings' (two words), whereas it appears hyphenated ('Post-disaster') everywhere else in the regulation; this map reproduces the source as filed. The e-Laws consolidation normalizes this single occurrence to the hyphenated form. This wording difference was not enacted by an amending regulation.
Provenance
OBC 1997 · split from 4.1.9.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 4.1.8.10. — Pro