9.26.11.

Version 0 — in force 31 December 2006

In force
Verified · covered Verified against the 2006-12-31–2007-04-01 consolidation, whose range covers the query date. How to read this

Provenance

OBC 1997 · continues from 9.26.11. — Pro

Base · O. Reg. 350/06 · ext← current

Original — base regulation

OBC 2012 · continues as 9.26.11. — Pro

9.26.11. — Built-Up Roofs

Content not available for this version.

9.26.11.1. — Quantity of Materials

(1) The quantities of bituminous materials used on built-up roofs shall conform to Table 9.26.11.1.

Text · e-Laws consolidated snapshot

Table 9.26.11.1. Quantities of Bitumen for Built-Up Roofs Forming Part of Sentence 9.26.11.1.(1)

Column 1

Column 2

Column 3

Type of Roof

Amount of Bitumen per Square Metre of Roof Surface

Mopping Coats Between Layers

Flood Coat

Asphalt and aggregate

1 kg

3 kg

Coal-tar and aggregate

1.2 kg

3.6 kg

Cold process roofing

0.75 L cold process cement

2 L cold process top coating

9.26.11.2. — Coal-Tar and Asphalt Products

(1) Coal-tar products and asphalt products shall not be used together in built-up roof construction.

Text · e-Laws consolidated snapshot

9.26.11.3. — Roof Felts

(1) Bitumen roofing felts shall be not less than No.15 felt.

Text · e-Laws consolidated snapshot

9.26.11.4. — Aggregate Surfacing

(1) Aggregate used for surfacing built-up roofs shall be clean, dry and durable and shall consist of particles of gravel, crushed stone or air-cooled blast furnace slag having a size of from 6 mm to 15 mm.

(2) The minimum amount of aggregate surfacing per square metre of roof surface shall be 15 kg gravel or crushed stone or 10 kg crushed slag.

Text · e-Laws consolidated snapshot

9.26.11.5. — Flashing

(1) Flashing shall conform to Subsection 9.26.4.

Text · e-Laws consolidated snapshot

9.26.11.6. — Number of Layers

(1) Built-up roofing shall consist of at least 3 mopped-down layers of roofing felt flood coated with bitumen.

Text · e-Laws consolidated snapshot

9.26.11.7. — Installation of Layers

(1) In hot process applications each layer of bitumen-saturated felt shall be laid while the bitumen is hot, with each layer overlapping the previous one.

(2) The full width under each lap referred to in Sentence (1) shall be coated with bitumen so that in no place does felt touch felt.

(3) Felt shall be laid free of wrinkles and shall be rolled directly into the hot bitumen and broomed forward and outward from the centre to ensure complete adhesion.

Text · e-Laws consolidated snapshot

9.26.11.8. — Roofing over Wood-Based Sheathing

(1) Except as permitted in Sentence (2), built-up roofing applied over wood, plywood, OSB or waferboard roof sheathing shall be laid over an additional base layer of felt laid dry over the entire roof deck with at least a 50 mm headlap and a 50 mm sidelap between each sheet.

(2) Where plywood, OSB or waferboard roof sheathing is used, the dry layer of felt required in Sentence (1) may be omitted when the joints are taped and the sheathing is primed with asphalt.

Text · e-Laws consolidated snapshot

9.26.11.9. — Attachment to Decking

(1) Roofing shall be securely attached to the decking or where insulation is applied above the deck, the insulation shall be securely attached to the deck before the first layer of felt is fastened to the insulation.

Text · e-Laws consolidated snapshot

9.26.11.10. — Cant Strips

(1) Except as permitted in Sentence (4), a cant strip shall be provided at the edges of roofs.

(2) No fewer than 2 plies of the roofing membrane shall be carried over the top of the cant strip.

(3) Flashing shall extend over the top of the cant strip and be shaped to form a drip.

(4) The cant strip required in Sentence (1) may be omitted where a gravel stop is provided at the edge of roofs.

(5) The roofing membranes shall be carried over the edge of the roof before the gravel stop is fastened and 2 plies of roofing membrane mopped to the top surface of the gravel stop referred to in Sentence (4) before the flood coat is applied.

(6) The gravel stop referred to in Sentence (4) shall extend over the edge of the roof to form a drip or shall be flashed so that the flashing extends over the edge to form a drip.

Text · e-Laws consolidated snapshot