(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 8.4.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 8.4. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 8.4. — Pro
8.4. — Class 2 Sewage Systems
Content not available for this version.
8.4.1. — General Requirements
Content not available for this version.
8.4.1.1. — Scope
(1) This Section applies to the construction of a Class 2 sewage system.
Text · e-Laws consolidated snapshot
8.4.1.2. — Application
(1) A Class 2 sewage system shall be designed only for the treatment and disposal of greywater.
(2) The total daily design flow for a Class 2 sewage system shall be calculated based on the fixtures discharging to the system as follows:
(a) 200 L per fixture unit where there is a supply of pressurized water, and
(b) 125 L per fixture unit where there is no supply of pressurized water.
Text · e-Laws consolidated snapshot
8.4.2. — Design and Construction Requirements
Content not available for this version.
8.4.2.1. — Construction Requirements
(1) The bottom of the pit shall be at least 900 mm above the high ground water table.
(2) The pit shall be constructed in such a manner as to prevent the collapse of its sidewalls.
(3) Any material used to support or form the sidewalls of the pit shall be an open jointed material of a type that will permit leaching from the pit.
(4) The pit shall be provided with a tight, strong cover that shall remain over the pit except when it is necessary to remove it for purposes of adding greywater to or removing greywater from the pit or for purposes of maintenance of the pit.
(5) The earth around the perimeter of the pit shall be raised or mounded to a height of at least 150 mm above ground level.
(6) The surface of the ground in the area of the pit shall be so graded that surface drainage in the area will be diverted away from the pit.
(7) The pit shall be surrounded on all sides and on its bottom by at least 600 mm of soil having a percolation time of less than 50 minutes.
Text · e-Laws consolidated snapshot
8.4.2.2. — Maximum Sewage Flow
(1) A Class 2 sewage system shall not be constructed where the daily design greywater flow to the system exceeds 1 000 L/day.
Text · e-Laws consolidated snapshot
8.4.2.3. — Sizing
(1) A Class 2 sewage system shall be designed and constructed so that the loading rate to the side walls shall be not more than the value calculated using the formula,
![]()
where,
LR = loading rate of the sidewalls in litres per day/m2, and
T = percolation time.
Text · e-Laws consolidated snapshot