OBC 2006 › Division C
2.4.2.2.
Version 1 — in force 2 April 2007
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- C
- Provision
- 2.4.2.2.
- Version
- v1
80. (1) Subject to subsection (2), this Regulation comes into force on the day it is filed.
Read directly from the regulation's own commencement section.
O. Reg. 137/07 · commencement 80(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- C
- Provision
- 2.4.2.2.
- Version
- v1
80. (1) Subject to subsection (2), this Regulation comes into force on the day it is filed.
Read directly from the regulation's own commencement section.
O. Reg. 137/07 · commencement 80(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · renumbered from 2.8.2.2. — Pro
Base · O. Reg. 350/06 · ext v0 →
O. Reg. 137/07, cl. 76 · ext ← current
In force 2007-04-02
OBC 2012 · renumbered to 2.4.2.1. — Pro
2.4.2.2. — Criteria
Comparing versions
Changed text stands out · unchanged is dimmed
v0 base
Earlier · 2006-12-31(1) A ruling made under clause 29 (1) (c) of the Act may only approve the use of an alternative material, system or building design in a manner,
(a) that will, in the opinion of the Minister, achieve the level of performance that is required by this Code, and
(b) that is consistent with,
(i) a decision of the Building Code Commission in respect of a dispute described in clause 24 (1) (a) of the Act,
(ii) an approval of the use of the material, system or building design in the whole of another province or territory in accordance with the law of that province or territory, or
(iii) a revision of the National Building Code of Canada or the National Plumbing Code of Canada that has been approved by the Canadian Commission on Building and Fire Codes.
v1 O. Reg. 137/07
Later · viewing · 2007-04-02(1) A ruling made under clause 29 (1) (c) of the Act may only approve the use of an alternative material, system or building design in a manner,
(a) that will, in the opinion of the Minister, achieve the level of performance that is required by this Code, and
(b) that is consistent with,
(i) a decision of the Building Code Commission in respect of a dispute described in clause 24 (1) (a) of the Act,
(ii) an approval of the use of the material, system or building design in the whole of another province or territory in accordance with the law of that province or territory, or
(iii) a revision of the CCBFC, “National Building Code of Canada” or the CCBFC, “National Plumbing Code of Canada” that has been approved by the Canadian Commission on Building and Fire Codes.
Provenance
OBC 1997 · renumbered from 2.8.2.2. — Pro
Base · O. Reg. 350/06 · ext v0 → comparing ×
O. Reg. 137/07, cl. 76 · ext ← current
In force 2007-04-02
OBC 2012 · renumbered to 2.4.2.1. — Pro