(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
80. (1) Subject to subsection (2), this Regulation comes into force on the day it is filed.
Read directly from the regulation's own commencement section.
O. Reg. 137/07 · commencement 80(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- C
- Provision
- 1.3.1.3.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
80. (1) Subject to subsection (2), this Regulation comes into force on the day it is filed.
Read directly from the regulation's own commencement section.
O. Reg. 137/07 · commencement 80(1)
Provenance
OBC 1997 · renumbered from 2.4.1.1B. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 137/07, cl. 73 · ext v1 →
In force 2007-04-02
O. Reg. 503/09, cl. 222(4) · ext v2 →
In force 2010-01-01
O. Reg. 503/09, cl. 222(3) · ext v3 →
In force 2011-01-01
Next: O. Reg. 137/07, cl. 73 · ext (not in force until 2007-04-02) v1 →
OBC 2012 · continues as 1.3.1.3. — Pro
1.3.1.3. — Period Within Which a Permit is Issued or Refused
Comparing versions
Changed text stands out · unchanged is dimmed
v0 base
Earlier · viewing · 2006-12-31(1) Subject to Sentences (2) and (3), if an application for a permit under subsection 8 (1) of the Act that meets the requirements of Sentence (5) is submitted to a chief building official, the chief building official shall, within the time period set out in Column 3 of Table 1.3.1.3. corresponding to the class of building described in Column 2 of Table 1.3.1.3. for which the application is made,
(a) issue the permit, or
(b) refuse to issue the permit and provide in writing all of the reasons for the refusal.
(2) If an application for a permit under subsection 8 (1) of the Act proposes construction or demolition of two or more buildings of different classes described in Column 2 of Table 1.3.1.3. that have different time periods in Column 3 of Table 1.3.1.3., the longer of the time periods shall be the time period for the purposes of Sentence (1).
(3) If an application for a permit under subsection 8 (1) of the Act proposes construction or demolition of a building described in Sentence (4), the time period for the purposes of Sentence (1) shall be the longer of,
(a) 10 days, and
(b) the time period corresponding to the class of the building described in Column 2 of Table 1.3.1.3. that the building in Sentence (4) serves, if any.
(4) A building referred to in Sentence (3) is,
(a) a structure occupying an area of 10 m2 or less that contains plumbing, including the plumbing appurtenant to it,
(b) plumbing not located in a structure,
(c) a sewage system, or
(d) a structure designated in Article 1.3.1.1. of Division A.
(5) The requirements for an application referred to in Sentence (1) for a permit under subsection 8 (1) of the Act are,
(a) that the application be made in the form described in Sentence 1.3.1.2.(2),
(b) that the application be signed by a person described in Clause 1.3.1.2.(1)(a) or (b),
(c) that all applicable fields on the application form and required schedules are completed,
(d) that all attachments indicated as being attached to the application are submitted with the application, and
(e) that the application be accompanied by the types and quantities of plans and specifications that are prescribed by the applicable by-law, resolution or regulation made under clause 7 (1) (b) of the Act.
(6) The time period described in Sentences (1) to (3) shall begin on the day following the later of,
(a) the day on which an application meeting the requirements of Sentence (5) is submitted to the chief building official, and
(b) the day on which payment is made of all fees that are required, under a by-law, regulation or resolution made under clause 7 (1) (c) of the Act, to be paid when the application is made.
(7) Subject to Sentences (8) and (9), the time periods described in Column 3 of Table 1.3.1.3. shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.
(8) The time period in Sentence (9) applies where,
(a) an application is made for the construction of a building that is served by a sewage system,
(b) construction is proposed in respect of the sewage system that serves the building, and
(c) a board of health, conservation authority, planning board or the council of an upper-tier municipality is responsible for the enforcement of the provisions of the Act and this Code related to the sewage system under section 3.1 of the Act or pursuant to an agreement under section 6.2 of the Act.
(9) The time period described in Sentences (1) to (3) for an application referred to in Clause (8)(a) shall begin on the day following the latest of,
(a) the day on which an application meeting the requirements of Sentence (5) is submitted to the chief building official,
(b) the day on which payment is made of all fees that are required, under a by-law, regulation or resolution made under clause 7 (1) (c) of the Act, to be paid when the application is made, and
(c) the day on which a permit for the construction of the sewage system referred to in Clause (8)(b) is issued.
v1 O. Reg. 137/07
Later · 2007-04-02(1) Subject to Sentences (2) and (3), if an application for a permit under subsection 8 (1) of the Act that meets the requirements of Sentence (5) is submitted to a chief building official, the chief building official shall, within the time period set out in Column 3 of Table 1.3.1.3. corresponding to the class of building described in Column 2 of Table 1.3.1.3. for which the application is made,
(a) issue the permit, or
(b) refuse to issue the permit and provide in writing all of the reasons for the refusal.
(2) If an application for a permit under subsection 8 (1) of the Act proposes construction or demolition of two or more buildings of different classes described in Column 2 of Table 1.3.1.3. that have different time periods in Column 3 of Table 1.3.1.3., the longer of the time periods shall be the time period for the purposes of Sentence (1).
(3) If an application for a permit under subsection 8 (1) of the Act proposes construction or demolition of a building described in Sentence (4), the time period for the purposes of Sentence (1) shall be the longer of,
(a) 10 days, and
(b) the time period corresponding to the class of the building described in Column 2 of Table 1.3.1.3. that the building in Sentence (4) serves, if any.
(4) A building referred to in Sentence (3) is,
(a) a structure occupying an area of 10 m2 or less that contains plumbing, including the plumbing appurtenant to it,
(b) plumbing not located in a structure,
(c) a sewage system, or
(d) a structure designated in Article 1.3.1.1. of Division A.
(5) The requirements for an application referred to in Sentence (1) for a permit under subsection 8 (1) of the Act are,
(a) that the application be made in the form described in Sentence 1.3.1.2.(2),
(b) that the application be signed by a person described in Clause 1.3.1.2.(1)(a) or (b),
(c) that all applicable fields on the application form and required schedules are completed,
(d) that all attachments indicated as being attached to the application are submitted with the application, and
(e) that the application be accompanied by the types and quantities of plans and specifications that are prescribed by the applicable by-law, resolution or regulation made under clause 7 (1) (b) of the Act.
(6) The time period described in Sentences (1) to (3) shall begin on the day following the later of,
(a) the day on which an application meeting the requirements of Sentence (5) is submitted to the chief building official, and
(b) the day on which payment is made of all fees that are required, under a by-law, regulation or resolution made under clause 7 (1) (c) of the Act, to be paid when the application is made.
(7) Subject to Sentences (8) and (9), the time periods described in Column 3 of Table 1.3.1.3. shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public.
(8) The time period in Sentence (9) applies where,
(a) an application is made for the construction of a building that is served by a sewage system,
(b) construction is proposed in respect of the sewage system that serves the building, and
(c) a board of health, conservation authority, planning board or the council of an upper-tier municipality is responsible for the enforcement of the provisions of the Act and this Code related to the sewage system under section 3.1 of the Act or pursuant to an agreement under section 6.2 of the Act.
(9) The time period described in Sentences (1) to (3) for an application referred to in Clause (8)(a) shall begin on the day following the latest of,
(a) the day on which an application meeting the requirements of Sentence (5) is submitted to the chief building official,
(b) the day on which payment is made of all fees that are required, under a by-law, regulation or resolution made under clause 7 (1) (c) of the Act, to be paid when the application is made, and
(c) the day on which a permit for the construction of the sewage system referred to in Clause (8)(b) is issued.
Provenance
OBC 1997 · renumbered from 2.4.1.1B. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 137/07, cl. 73 · ext v1 →
In force 2007-04-02 comparing ×
O. Reg. 503/09, cl. 222(4) · ext v2 →
In force 2010-01-01 compare
O. Reg. 503/09, cl. 222(3) · ext v3 →
In force 2011-01-01 compare
Next: O. Reg. 137/07, cl. 73 · ext (not in force until 2007-04-02) v1 →