240. (1) Subject to subsections (2), (3), (4), (5), (6) and (7), this Regulation comes into force on the later of January 1, 2010 and the day this Regulation is filed.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 9.19.1.3.
- Version
- v1
240. (1) Subject to subsections (2), (3), (4), (5), (6) and (7), this Regulation comes into force on the later of January 1, 2010 and the day this Regulation is filed.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 9.19.1.3. — Pro
Base · O. Reg. 350/06 · ext v0 →
O. Reg. 503/09, cl. 161 · ext ← current
In force 2010-01-01
OBC 2012 · continues as 9.19.1.3. — Pro
9.19.1.3. — Clearances
Comparing versions
Changed text stands out · unchanged is dimmed
v0 base
Earlier · 2006-12-31(1) Except as provided in Sentence (2), where venting is provided to a roof joist space, not less than 63 mm of space shall be provided between the top of the insulation and the underside of the roof sheathing.
(2) Where venting is provided at the junction of sloped roofs and exterior walls and where preformed baffles are used to contain the insulation, the baffles shall,
(a) provide an unobstructed air space between the insulation and the underside of the roof sheathing, that is,
(i) not less than 25 mm in dimension, and
(ii) of sufficient cross area to meet the attic or roof space venting requirements of Article 9.19.1.2., and
(b) extend vertically not less than 50 mm vertically above the top of the insulation.
(3) Ceiling insulation shall be installed in a manner that will not restrict a free flow of air through roof vents or through any portion of the attic or roof space.
v1 O. Reg. 503/09
Later · viewing · 2010-01-01(1) Except as provided in Sentence (2), where venting is provided to a roof joist space, not less than 63 mm of space shall be provided between the top of the insulation and the underside of the roof sheathing.
(2) Where venting is provided at the junction of sloped roofs and exterior walls and where preformed baffles are used to contain the insulation, the baffles shall,
(a) provide an unobstructed air space between the insulation and the underside of the roof sheathing, that is,
(i) not less than 25 mm in dimension, and
(ii) of sufficient cross area to meet the attic or roof space venting requirements of Article 9.19.1.2., and
(b) extend vertically not less than 50 mm above the top of the insulation.
(3) Ceiling insulation shall be installed in a manner that will not restrict a free flow of air through roof vents or through any portion of the attic or roof space.
Provenance
OBC 1997 · continues from 9.19.1.3. — Pro
Base · O. Reg. 350/06 · ext v0 → comparing ×
O. Reg. 503/09, cl. 161 · ext ← current
In force 2010-01-01
OBC 2012 · continues as 9.19.1.3. — Pro