OBC 2006 › Division B
8.9.2.4.
Version 0 — in force 31 December 2006
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 8.9.2.4.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 8.9.2.4.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 8.9.2.4. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 8.9.2.4. — Pro
8.9.2.4. — Shallow Buried Trenches
(1) Every person operating a treatment unit that is designed and constructed to produce effluent described in Column 3 of Table 8.6.2.2.A.v1 shall, at the intervals described in Sentence (2),
(a) take a grab sample of the effluent to determine whether it complies with the levels contained in Column 3 of Table 8.6.2.2.A.v1 for BOD5 and suspended solids,
(b) carry out the sampling required by Clause (1)(a) in accordance with the methods described in the APHA/AWWA/WEF, “Standard Methods for the Examination of Water and Wastewater”, and
(c) promptly submit the results of the sampling required by Clause (1)(a) to the chief building official.
(2) The sampling required by Clause (1)(a) shall be conducted,
(a) initially, once during the first 12 months after the sewage system was put into use, and
(b) after that, once during every 12 month period, at least 10 months and not more than 18 months after the previous sampling has been completed.
Text · e-Laws consolidated snapshot
Provenance
OBC 1997 · continues from 8.9.2.4. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 8.9.2.4. — Pro