(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 8.8.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 8.8. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 8.8. — Pro
8.8. — Class 5 Sewage Systems
Content not available for this version.
8.8.1. — Application
Content not available for this version.
8.8.1.1. — Prohibited Installation
(1) Except as provided in Article 8.8.1.2., a Class 5 sewage system shall not be installed.
Text · e-Laws consolidated snapshot
8.8.1.2. — Acceptable Installation
(1) A Class 5 sewage system may be installed in the following circumstances:
(a) where the proposed use of the sewage system is for a temporary operation, excluding seasonal recreational use, not exceeding 12 months in duration,
(b) to remedy an unsafe sewage system where the remediation of the unsafe condition by the installation of a Class 4 sewage system is impracticable,
(c) to upgrade a sewage system serving an existing building, where upgrading through the use of a Class 4 sewage system is not possible due to lot size, site slope or clearance limitations, or
(d) as an interim measure for a lot or parcel of land until municipal sewers are available, provided that the municipality undertakes to ensure the continued operation of an approved hauled sewage system until the municipal sewers are available.
(2) Where a Class 5 sewage system is installed, a written agreement for the disposal of sanitary sewage from the sewage system shall be entered into with a hauled sewage system operator.
Text · e-Laws consolidated snapshot
8.8.2. — General Requirements
Content not available for this version.
8.8.2.1. — Construction Requirements
(1) All Class 5 sewage systems shall be equipped with a device that shall produce an audible and visual warning alarm so located to warn that the sewage system is nearing capacity.
(2) The device required in Sentence (1) shall be designed to provide suitable advance warning to the building occupants considering,
(a) the total daily design sanitary sewage flow,
(b) the location of the Class 5 sewage system, and
(c) the response time of the hauled sewage system contractor.
(3) Except as provided in Sentence (4) all holding tanks shall be provided with a vent that,
(a) is not less than 3 inch trade size,
(b) terminates at least,
(i) 300 mm above finished grade with a vent cap, or
(ii) 600 mm above finished grade with a vent cap when the holding tank is located in an area subject to flooding, and
(c) terminates at least 3.5 m away from any air inlet, window, or door.
(4) A vent from a holding tank may connect into the venting system of the building served by the holding tank provided that,
(a) the vent is not less than 3 in. trade size, and
(b) the installation of the vent shall conform to the requirements in Part 7.
Text · e-Laws consolidated snapshot
8.8.2.2. — Sizing of Holding Tanks
(1) All holding tanks used in residential dwellings shall have a minimum 7 day holding capacity based on the total daily design sanitary sewage flow.
Text · e-Laws consolidated snapshot
Provenance
OBC 1997 · continues from 8.8. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 8.8. — Pro