8.6.1. — General Requirements

Content not available for this version.

8.6.1.1. — Scope

(1) This Section applies to the construction of a Class 4 sewage system.

Text · e-Laws consolidated snapshot

8.6.1.2. — General Requirements

(1) The treatment unit shall be connected to a leaching bed constructed in accordance with the requirements of Section 8.7.

Text · e-Laws consolidated snapshot

8.6.1.3. — Pumps and Siphons

(1) Where the total length of distribution pipe required is 150 m or more, the sewage system shall have at least one pump or a siphon contained in a dosing tank that may be a separate compartment within the tank structure, for distribution of the effluent.

(2) Alternating siphons shall not be installed in a sewage system.

(3) Where 2 or more pumps are employed within a dosing tank, the pumps shall be designed such that the pumps alternate dosing, and dosing shall continue in the event that one pump fails.

(4) Where a pump or siphon is required, the pump or siphon shall be designed to discharge a dose of at least 75% of the internal volume of the distribution pipe within a time period not exceeding fifteen minutes.