(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
240. (1) Subject to subsections (2), (3), (4), (5), (6) and (7), this Regulation comes into force on the later of January 1, 2010 and the day this Regulation is filed.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 8.2.2.3.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next one commenced. What follows is that next version’s commencement — the event that ended this one.
240. (1) Subject to subsections (2), (3), (4), (5), (6) and (7), this Regulation comes into force on the later of January 1, 2010 and the day this Regulation is filed.
Read directly from the regulation's own commencement section.
O. Reg. 503/09 · commencement 240(1)
Provenance
OBC 1997 · continues from 8.2.2.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 503/09, cl. 118 · ext v1 →
In force 2010-01-01
Next: O. Reg. 503/09, cl. 118 · ext (not in force until 2010-01-01) v1 →
OBC 2012 · continues as 8.2.2.3. — Pro
8.2.2.3. — Septic Tanks
Comparing versions
Changed text stands out · unchanged is dimmed
v0 base
Earlier · viewing · 2006-12-31(1) The minimum working capacity of a septic tank shall be the greater of 3 600 L and,
(a) in residential occupancies, twice the daily design sanitary sewage flow, or
(b) in non-residential occupancies, three times the daily design sanitary sewage flow.
(2) Every septic tank shall be constructed in such a manner that any sanitary sewage flowing through the tank will pass through at least 2 compartments.
(3) The working capacity of the compartments required in Sentence (2) shall be sized such that,
(a) the first compartment is at least 1.3 times the daily design sanitary sewage flow but in no case less than 2 400 L, and
(b) each subsequent compartment shall be at least 50% of the first compartment.
(4) Where multiple tanks are to be used to meet the requirements of Sentences (2) and (3), the tanks shall be connected in series such that,
(a) the first tank in the series shall have at least a capacity as calculated in Clause (3)(a), however at no time shall a tank having a working capacity of less than 3 600 L be used,
(b) all additional tanks after the first tank, excluding pump or dosing tanks shall have at least a working capacity equal to Clause (3)(b),
(c) the pipe between the outlet of one tank and the inlet of the next tank in the series shall have a minimum slope of 2 per cent,
(d) there shall be no partitions in the tank except where a partition is required to maintain the structural integrity of the tank, in which case openings within the partition shall be provided to allow the free movement of sanitary sewage throughout the tank, and
(e) all piping between tanks shall be continuous and shall be connected to the tank through the use of flexible watertight seals that will permit differential movement between the tanks.
(5) Partitions separating the septic tank into compartments shall extend at least 150 mm above the liquid level at the outlet, and there shall be one or more openings through or above the partition.
(6) The openings required between compartments referred to in Sentence (2) shall have a total cross-sectional area of at least three times the area of the inlet pipe and be located between the top and a level 150 mm above the liquid level at the outlet to provide for the free flow of air between compartments.
(7) Sanitary sewage shall pass from one compartment to another of the septic tank by means of either,
(a) a device similar to that described in CSA B66, “Design, Material, and Manufacturing Requirements for Prefabricated Septic Tanks and Sewage Holding Tanks” for outlet devices, or
(b) through two or more openings through the partition located in a horizontal line, and evenly spaced across the width of the partition, centred at approximately 40% of the liquid depth below the surface of the liquid, and having a total area of between three and five times that of the cross-sectional area of the inlet pipe.
(8) A septic tank shall be of such design and construction as will permit the collection and holding of sanitary sewage in it to a depth of not less than 1 200 mm except that a depth of not less than 900 mm is permitted where the excavation is in rock, or to avoid rupture or displacement of the tank due to ground water pressure.
(9) Except as provided in Sentences (10) and (11), every septic tank shall be installed in such a manner that the access openings are located not more than 300 mm below the ground surface.
(10) Where the top of the septic tank is located more than 300 mm below the ground surface, it shall be equipped with risers that extend from the access opening of the septic tank to within 300 mm of the ground surface.
(11) Where risers are used they shall conform to the requirements of CSA B66, “Design, Material, and Manufacturing Requirements for Prefabricated Septic Tanks and Sewage Holding Tanks”, and shall have adequate access openings to allow for regular maintenance of the septic tank.
v1 O. Reg. 503/09
Later · 2010-01-01(1) The minimum working capacity of a septic tank shall be the greater of 3 600 L and,
(a) in residential occupancies, twice the daily design sanitary sewage flow, or
(b) in non-residential occupancies, three times the daily design sanitary sewage flow.
(2) Every septic tank shall be constructed in such a manner that any sanitary sewage flowing through the tank will pass through at least 2 compartments.
(3) The working capacity of the compartments required in Sentence (2) shall be sized such that,
(a) the first compartment is at least 1.3 times the daily design sanitary sewage flow but in no case less than 2 400 L, and
(b) each subsequent compartment shall be at least 50% of the first compartment.
(4) Where multiple tanks are to be used to meet the requirements of Sentences (2) and (3), the tanks shall be connected in series such that,
(a) the first tank in the series shall have at least a capacity as calculated in Clause (3)(a), however at no time shall a tank having a working capacity of less than 3 600 L be used,
(b) all additional tanks after the first tank, excluding pump or dosing tanks shall have at least a working capacity equal to Clause (3)(b),
(c) the pipe between the outlet of one tank and the inlet of the next tank in the series shall have a minimum slope of 2 per cent,
(d) there shall be no partitions in the tank except where a partition is required to maintain the structural integrity of the tank, in which case openings within the partition shall be provided to allow the free movement of sanitary sewage throughout the tank, and
(e) all piping between tanks shall be continuous and shall be connected to the tank through the use of flexible watertight seals that will permit differential movement between the tanks.
(5) Partitions separating the septic tank into compartments shall extend at least 150 mm above the liquid level at the outlet, and there shall be one or more openings through or above the partition.
(6) The openings required between compartments referred to in Sentence (2) shall have a total cross-sectional area of at least three times the area of the inlet pipe and be located between the top and a level 150 mm above the liquid level at the outlet to provide for the free flow of air between compartments.
(7) Sanitary sewage shall pass from one compartment to another of the septic tank by means of either,
(a) a device similar to that described in CSA B66, “Design, Material, and Manufacturing Requirements for Prefabricated Septic Tanks and Sewage Holding Tanks” for outlet devices, or
(b) through two or more openings through the partition located in a horizontal line, and evenly spaced across the width of the partition, centred at approximately 40% of the liquid depth below the surface of the liquid, and having a total area of between three and five times that of the cross-sectional area of the inlet pipe.
(8) A septic tank shall be of such design and construction as will permit the collection and holding of sanitary sewage in it to a depth of not less than 1 000 mm except that a depth of not less than 900 mm is permitted where the excavation is in rock, or to avoid rupture or displacement of the tank due to ground water pressure.
(9) Except as provided in Sentences (10) and (11), every septic tank shall be installed in such a manner that the access openings are located not more than 300 mm below the ground surface.
(10) Where the top of the septic tank is located more than 300 mm below the ground surface, it shall be equipped with risers that extend from the access opening of the septic tank to within 300 mm of the ground surface.
(11) Where risers are used they shall conform to the requirements of CSA B66, “Design, Material, and Manufacturing Requirements for Prefabricated Septic Tanks and Sewage Holding Tanks”, and shall have adequate access openings to allow for regular maintenance of the septic tank.
Provenance
OBC 1997 · continues from 8.2.2.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
O. Reg. 503/09, cl. 118 · ext v1 →
In force 2010-01-01 comparing ×
Next: O. Reg. 503/09, cl. 118 · ext (not in force until 2010-01-01) v1 →