(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 7.4.6.3.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · continues from 7.4.6.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 7.4.6.3. — Pro
7.4.6.3. — Sumps or Tanks
(1) Only piping that is too low to drain into a building sewer by gravity shall be drained to a sump or receiving tank.
(2) Where the sump or tank receives sanitary sewage it shall be water and air-tight and shall be vented.
(3) Equipment such as a pump or ejector that can lift the contents of the sump or tank and discharge it into the sanitary building drain or sanitary building sewer shall be installed.
(4) Where the equipment does not operate automatically the capacity of the sump shall be sufficient to hold at least a 24 hours accumulation of liquid.
(5) Where there is a building trap the discharge pipe from the equipment shall be connected to the sanitary building drain downstream of the trap.
(6) The discharge pipe from every pumped sanitary sewage sump shall be equipped with a union, a check valve and a shut-off valve installed in that sequence in the direction of discharge.
(7) The discharge piping from a pump or ejector shall be sized for optimum flow velocities at pump design conditions.
(8) The discharge pipe from every pumped storm sewage sump shall be equipped with,
(a) a union and a check valve installed in that sequence in the direction of discharge and pumped to above grade level, or
(b) a union, a check valve and a shut off valve installed in that sequence in the direction of discharge.
Text · e-Laws consolidated snapshot
Provenance
OBC 1997 · continues from 7.4.6.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 7.4.6.3. — Pro