(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 5.4.1.2.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · split from 5.4.1.2. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 5.4.1.2. — Pro
5.4.1.2. — Air Barrier System Properties
(1) Except as provided in Sentence (2), materials intended to provide the principal resistance to air leakage shall have an air leakage characteristic not greater than 0.02 L/( s·m²) measured at an air pressure difference of 75 Pa.
(2) The air leakage limit specified in Sentence (1) is permitted to be increased where it can be shown that the higher rate of leakage will not adversely affect any of,
(a) the health or safety of building users,
(b) the intended use of the building, or
(c) the operation of building services.
(3) The air barrier system shall be continuous,
(a) across construction, control and expansion joints,
(b) across junctions between different building assemblies, and
(c) around penetrations through the building assembly.
(4) The structural design of air barrier systems installed in assemblies subject to air pressure loads shall comply with Article 5.1.4.1. and Subsection 5.2.2.
Editor's note
In Sentence 5.4.1.2.(1), the air-leakage unit expression is filed in O. Reg. 350/06 with a space after the opening parenthesis ('0.02 L/( s·m²)'); this map reproduces the source as filed. The e-Laws consolidation removes that space ('0.02 L/(s·m²)'). This punctuation difference was not enacted by an amending regulation.
Provenance
OBC 1997 · split from 5.4.1.2. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 5.4.1.2. — Pro