(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
This looks wrong
Tell us what is wrong and we will verify & correct our mapping.
- Edition
- OBC_2006
- Division
- B
- Provision
- 4.2.2.2.
- Version
- v0
(1) This Regulation comes into force on December 31, 2006.
Read directly from the regulation's own commencement section.
O. Reg. 350/06 · commencement 2.2.1.1(1)
This version stayed in force until the next edition replaced it. What follows is that edition’s base regulation’s commencement — the takeover that ended this one.
(1) Subject to Sentences (2) and (3), this Regulation comes into force on January 1, 2014.
Read directly from the regulation's own commencement section.
O. Reg. 332/12 · commencement 4.4.1.1(1)
Provenance
OBC 1997 · renumbered from 4.2.2.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 4.2.2.2. — Pro
4.2.2.2. — Field Review
(1) A field review shall be carried out by the designer or by another suitably qualified person to ascertain that the subsurface conditions are consistent with the design and that construction is carried out in accordance with the design and good engineering practice.
(2) The review required in Sentence (1) shall be carried out,
(a) on a continuous basis,
(i) during the construction of all deep foundation units with all pertinent information recorded for each foundation unit,
(ii) during the installation and removal of retaining structures and related backfilling operations, and
(iii) during the placement of engineered fills that are to be used to support the foundation units, and
(b) as required, unless otherwise directed by the chief building official,
(i) in the construction of all shallow foundation units, and
(ii) in excavating, dewatering and other related works.
Text · e-Laws consolidated snapshot
Provenance
OBC 1997 · renumbered from 4.2.2.3. — Pro
Base · O. Reg. 350/06 · ext← current
Original — base regulation
OBC 2012 · continues as 4.2.2.2. — Pro